Artemis Gold shares rise on permit for Blackwater mine works start

Artemis Gold (TSXV: ARTG) announced Thursday the approval of its BC Mines Act Permit allowing it to start major construction of the Blackwater project in central British Columbia, with the initial gold pour expected in the second half of 2024.

Mar 9, 2023
Artemis Gold shares rise on permit for Blackwater mine works start
Site of the Blackwater gold project in central B.C.
AdSpace

Located about 446 km northeast of Vancouver, the Blackwater project comprises the construction, operation and closure of an open-pit gold mine and ore processing facilities that will be developed in multiple stages.

“The approval of the BC Mines Act Permit is the culmination of a substantial amount of work completed by our team in collaboration with our First Nation partners and the provincial government,” Artemis chairman and CEO Steven Dean said in a news release Thursday. 

The Blackwater mine is estimated to be the largest gold project in the Cariboo region of B.C. in more than a decade, the company said, and can support regional employment over multiple decades with the potential to be extended through further exploration.

In addition, the Blackwater mine “has been designed to have one of the smallest carbon footprints for an open pit gold project in the world, with a defined path forward to substantially reduce that footprint further and potentially achieve net zero carbon emissions through the integration of a zero-exhaust-emission haul fleet by 2029,” Dean said.

The mine will be connected to the BC Hydro grid, which is powered by hydroelectricity. This provides the foundation for Blackwater to be developed into one of the lowest greenhouse gas emitting open pit mining operations in the world, according to Artemis. The company also invested in a fully electrified process plant with all diesel and propane components replaced with electric equipment.

Artemis is planning an open pit mine with a 22-year life using gravity and conventional cyanidation methods for gold recovery.

Over that period, it is expected to produce an average of 339,000 oz. of gold per year. Life-of-mine capital costs are estimated at $2.25 billion, beginning with $645.2 million to be spent before production begins next year.

As part of the permitting process, Artemis said it also collaborated with the federal and provincial governments as well as First Nations communities on the development of environmental management plans related to offsetting of caribou and fish habitats, wetlands, and conservation and enhancement activities.

Premier David Eby said in the release that Blackwater will “put lots of people to work and create a wide range of opportunities and benefits for local businesses, communities and First Nations while ensuring the highest standards of environmental protection, mitigation and sustainability.”

Josie Osborne, the provincial Minister of Energy, Mines and Low Carbon Innovation, added: “British Columbians will benefit from hundreds of new jobs from this new mine, with both its construction and multiple decades of operation.”

An economic impact study completed by KPMG on the Blackwater project in November 2020 anticipates that it will create 457 direct full-time jobs per year over the operating life of the mine, and 825 direct full-time jobs per year during the construction/expansion phases of mine development.

Additionally, the mine is expected to contribute $13.2 billion to the provincial economy over the life of the mine, including $2.3 billion to provincial revenues, the report said.

Artemis shares traded at $4.40 on Thursday afternoon in Toronto, in a 52-week window of $3.48 and $7.93, valuing the company at $850.2 million.